Customise Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorised as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyse the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customised advertisements based on the pages you visited previously and to analyse the effectiveness of the ad campaigns.

No cookies to display.

Thalia Mara Hall Updates – Week 13

Thalia Mara Hall Updates – Week 13

There continues to be notable progress on the Thalia Mara Hall remediation project.  We will continue to publish this information as additional developments are made. The current standing of the project is listed below – as of Thursday, December 5.

 

  • Encapsulation – Theater 30% completed (The term “encapsulation” means enclosing contaminated or hazardous materials within a barrier to prevent pollutants from spreading into the environment)
  • HVAC Cleaning 25% completed
  • HVAC Encapsulation to start 12-2
  • Lobby Mitigation 80% completed
  • Office area Mitigation 90%
  • Theater Mitigation 20% completed

 

Next Steps:

  1. Fire Marshal check-in next week to discuss fire curtain replacement
  2. Proposals for rigging are currently under review

Previous Updates:

Week 1 (9/12/24): Week 1
Week 2 (9/19/24): Week 2
Week 3 (9/26/24): Week 3
Week 4 (10/3/24): Week 4
Week 5 (10/10/24): Week 5
Week 6 (10/18/24): Week 6
Week 7 (10/24): Week 7
Week 8 (10/31/24): N/A – Progress Continues
Week 9 (11/7/24): Week 9
Week 10 (11/14/24): N/A – Progress Continues
Week 11 (11/21/24): N/A – Progress Continues
Week 12 (11/24/28): N/A: Thanksgiving Holiday Closure