Thalia Mara Hall Updates – Week 13
Post

Thalia Mara Hall Updates – Week 13

There continues to be notable progress on the Thalia Mara Hall remediation project.  We will continue to publish this information as additional developments are made. The current standing of the project is listed below – as of Thursday, December 5.   Encapsulation – Theater 30% completed (The term “encapsulation” means enclosing contaminated or hazardous materials...

Thalia Mara Hall
Post

Thalia Mara Hall Updates – Week 9  

The Thalia Mara Hall remediation project has begun. We will continue to publish updates every Thursday as additional developments are made.    The following progress has been made since the start of remediation:  Equipment Arrival: All necessary equipment and supplies are now on site. Climate Control: Temporary climate control systems have been installed and are operational....

Thalia Mara Hall Updates – Week 7
Post

Thalia Mara Hall Updates – Week 7

The City of Jackson is currently awaiting Bids for Remediation Procurement to ensure we get the best pricing and least disruptive timeline regarding Thalia Mara Hall. We will continue to publish updates every Thursday as additional developments are made.   10/21: Project Kick-off Meeting – The teams from the city, Guarantee Restoration, and CTEH met...

Thalia Mara Hall Updates – Week 6
Post

Thalia Mara Hall Updates – Week 6

The City of Jackson is currently awaiting Bids for Remediation Procurement to ensure we get the best pricing and least disruptive timeline regarding Thalia Mara Hall. We will continue to publish updates every Thursday as additional developments are made.   10/15: Guarantee Restoration Services, LLC selected for remediation – After careful review of submissions, Guarantee...

Thalia Mara Hall Updates – Week 5
Post

Thalia Mara Hall Updates – Week 5

The City of Jackson is currently awaiting Bids for Remediation Procurement to ensure we get the best pricing and least disruptive timeline regarding Thalia Mara Hall. We will continue to publish updates every Thursday as additional developments are made. 10/11: Proposals due Next Steps: 10/14: Proposal Review 10/17: Scheduled theater rigging inspection Previous Updates: Week...

Post

Thalia Mara Hall Updates – Week 4

The City of Jackson is currently awaiting Bids for Remediation Procurement to ensure we get the best pricing and least disruptive timeline regarding Thalia Mara Hall. We will continue to publish updates every Thursday as additional developments are made. 9/24: CTEH submitted a follow-up Proposal to their Initial Assessment 10/1: Request for Bids for Remediation Procurement 10/3: Mandatory Site...

Post

Thalia Mara Hall Updates – Week 3

The City of Jackson is currently awaiting additional proposals to ensure we get the best pricing and least disruptive timeline regarding Thalia Mara Hall. We will continue to publish updates every Thursday as additional developments are made. 9/23: Contractor site visits for proposal submissions 9/24: Contractor site visits for proposal submissions 9/25: Chiller connection and testing, Fire Alarm...

Post

Thalia Mara Hall Update – Week 2 

Thalia Mara Hall Update w/ all Major Milestones 9/19/24 The City of Jackson is currently awaiting additional proposals to ensure we get the best pricing and least disruptive timeline regarding Thalia Mara Hall. We will continue to publish updates every Thursday as additional developments are made. 9/11: We were visited by the Fire Marshall.  The...

Post

Thalia Mara Hall Update w/ all Major Milestones

Thalia Mara Hall Update w/ all Major Milestones 9/12/24 The City of Jackson is currently awaiting quotes from additional vendors to ensure we get the best pricing and least disruptive timeline regarding Thalia Mara Hall. We will continue to publish weekly updates as additional developments play out. The scheduling below was based on the availability...

Post

Update: Environmental Report on Thalia Mara Hall 

Earlier this month, the City of Jackson was forced to shut down Thalia Mara Hall after early microbial activity was found. We quickly alerted the public and the media of this development when the information was made available to us. City officials then immediately worked to hire a contractor to analyze the environment, provide a...