Thalia Mara Hall Updates – Week 6

Thalia Mara Hall Updates – Week 6

The City of Jackson is currently awaiting Bids for Remediation Procurement to ensure we get the best pricing and least disruptive timeline regarding Thalia Mara Hall. We will continue to publish updates every Thursday as additional developments are made.

 

  1. 10/15: Guarantee Restoration Services, LLC selected for remediation – After careful review of submissions, Guarantee Restoration Services proposal was determined the best option. The City of Jackson appreciates the diligent and competitive effort of all the participating entities and looks forward to continued partnership in the future, as all groups put their best foot forward and were resolute in their commitment to the city’s success. The contracts are currently running their course through respective legal review and signatory processes.
  2. 10/17: Rigging inspection commenced – Schuler Shook Theater Planning began thorough testing of the rigging and accompanying systems in the theater and will continue their assessment through this week.

 

Next Steps:

 

  1. 10/21: Master Schedule review – A master schedule for remediation is being compiled and will be reviewed Monday 10/21 ahead of notice to proceed.
  2. Week of 10/21: Project start will be greenlit and start date announced.

 