The Thalia Mara Hall remediation project has begun. We will continue to publish updates every Thursday as additional developments are made.
The following progress has been made since the start of remediation:
- Equipment Arrival: All necessary equipment and supplies are now on site.
- Climate Control: Temporary climate control systems have been installed and are operational.
- Safety Measures: Protective safety measures have been established throughout the facility.
- Air Quality Control: Air quality systems are active in most areas to ensure a safe environment.
- Asbestos Removal Permit: The required permit for asbestos removal has been approved.
- Basement Cleaning: 80% of the basement contents have been cleaned.
- Structural Cleaning: Half of the structural cleaning in the basement is complete.
- Installation Equipment: Aerial lifts have arrived, and 70% of the scaffolding has been set up.
- Rigging Analysis: The rigging inspection report has been received, response determination in progress
- Roofing Inspection: A roofing inspection and planned repairs are running concurrent to the remediation process
Next Steps:
- Remediation and repair schedule will continue, progress will be reflected in these updates.